Case Study: Process to Procure a Transmission Operation System
ScottMadden assisted an independent energy transmission company in choosing a new transmission operation system provider with vendor selection and contract negotiation.
- The client was building a new transmission operations center to assume operation of the energy transmission grid
- The implementation of a new transmission operation system (TOS) was a critical component of assuming operations of the transmission system
- The client did not have dedicated internal staff to develop the technical specifications for this complex computer system
- This was one of many initiatives undertaken by the company at same the time
- Managed the process to develop detailed technical specifications for the TOS
- Raised key decisions to client management as the functionality for the system was specified to ensure that all internal requirements were met
- Worked to ensure that the clients specifications were met in the most cost effective manner through a competitive bid vendor selection process, site visits and detailed contract negotiation
- Served as the client representative through contract negotiation
- The client selected a TOS vendor through a competitive bid vendor selection
- The client implemented a state-of-the-art TOS system
- The system required minimal customization, saving the client money
- System deployment was completed six months prior to the date the client was scheduled to assume operation of the energy transmission grid, allowing ample time for parallel operations